Anchor Flange Foundation & Main Gas Header Excavation
Main Gas Header Escavation
Jacket Water Install Update
Area 4 Header Install
Area 3 Filter Separator Install
Area 1 Header Install Update
October 2024
Dual Cranes
Area 3 Metering Install
Main Header Pipe Backfill
Main Header Excavation Open
Inlet Gas Cooler Install
Area 4 Header Pipe Install
November 2024
Site Overview
Areas 1, 2, and 3
Site Overview
Compressor Building
December 2024
Area 3 Post-Backfill
Wire At Unit 1 Compressor
Three Phase Separator
Scrubber Area Tubing
Priming Bolts
Manlift Work at Generator
Inlet Gas Coolers
Fabricating Generator Exhaust Piping
ESD Button Installed
Conduit at Control Building
Compressor Building Instruments and Tubing
Cables Pulled to Generator
Blowdown Silencer Area Tubing
Blasting 1500# System Header Pipe
Area 3 Cable
Western Metering Tie-Ins
Southern Tie-Ins
Site Overview
Dehy Area
Compressor Building Headers
We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it and accept our cookies. If you do not accept, it is your responsibility to leave this site.OkNoPrivacy policy